How this calculation works
Start with the geometric volume of a rectangular slab, then add your chosen allowance. All dimensions must be in metres. Thickness of 100 mm is 0.1 m.
Order volume = length × width × thickness × (1 + allowance/100)A worked example
A 5 m by 4 m slab, 0.1 m thick, needs 2 m³ geometrically or 2.2 m³ with 10% allowance.
Good to know
Quantity estimate only, not a mix design or structural specification. Confirm delivery increments, site conditions and ordering allowances with the supplier.
A small thickness change affects the entire slab
For a 5 by 4 m slab, every extra centimetre of thickness adds 0.2 m³. That comes from 20 m² multiplied by 0.01 m. Thickness can look small on a drawing while having a noticeable effect on a concrete order.
The allowance is applied to the complete geometric volume, not to each dimension. Increasing all three dimensions by 10% would increase volume by 33.1%, a different operation from adding a 10% quantity allowance.
The volume converter can express the calculated solid volume in another volume unit. It does not add waste, compaction or delivery allowances.
Measure, convert and confirm before ordering
All dimensions must be in metres: 100 mm thickness means 0.1 m. Check formwork dimensions, uneven ground and any separate footings or thickened edges. A rectangular slab formula cannot infer those features.
The result estimates quantity, not strength, reinforcement or mix proportions. Ask the supplier about delivery increments and confirm a project-specific allowance rather than treating the default percentage as a construction standard.
A few questions, answered
Does the allowance change slab thickness?
No. It increases the estimated order quantity after calculating the entered geometric volume.
Does this specify a structural slab design?
No. Thickness, reinforcement and mix design require appropriate project specifications.